PMP (2026 exam): sample questions with answers
20 sample questions, each with the correct answer and an explanation. They come from the question bank and follow the exam format.
Questions are written from samples prepared by specialists in the field and follow the official exam format.
1. Market conditions, government regulations and the organisation's culture, which the team cannot control, are examples of:
- A) Organisational process assets
- B) Work performance data
- C) Deliverables
- D) Enterprise environmental factors
Show the answer and explanation
Correct answer: D
EEFs are internal and external conditions outside the team's control.
2. An insurance company's claims process takes 30 days, although only about 3 days of actual work are done on each claim. A project has been set up to speed up the process. Which technique would best show where time is lost in the flow of work to the customer?
- A) To list stakeholders
- B) To estimate costs
- C) To assign roles
- D) To identify waste and delays in the flow of work to the customer
Show the answer and explanation
Correct answer: D
Value stream mapping shows the flow of work to the customer and exposes waste, waiting and bottlenecks. Listing stakeholders, estimating costs or assigning roles does not.
3. According to the Agile Manifesto, which is valued more?
- A) Comprehensive documentation over working software
- B) Following a plan over responding to change
- C) Processes and tools over individuals
- D) Customer collaboration over contract negotiation
Show the answer and explanation
Correct answer: D
The Manifesto values customer collaboration over contract negotiation.
4. Who is usually responsible for tracking benefits realisation after the project closes?
- A) Nobody, because the project is closed
- B) The benefits owner in the business, as set out in the benefits management plan
- C) The external auditor
- D) The project team, indefinitely
Show the answer and explanation
Correct answer: B
In short: The business benefits owner. This is the correct answer.
5. In which organisational structure does the project manager usually have the greatest authority?
- A) Functional
- B) Weak matrix
- C) Balanced matrix
- D) Projectized
Show the answer and explanation
Correct answer: D
In a projectized structure the team reports to the project manager, giving the most authority. In a functional structure the functional manager holds it.
6. An agile team has spent three meetings debating which test automation tool to use and still cannot reach consensus. The decision is now blocking work on the current sprint. The team charter says that if consensus is not reached within a time-box, the accountable person decides. What should the project manager do?
- A) Keep discussing until everyone agrees
- B) Use the team's agreed decision rule, such as a time-box followed by a decision by the accountable person
- C) Choose the cheapest tool without discussion
- D) Let each member use a different tool
Show the answer and explanation
Correct answer: B
Apply the agreed decision rule: after the time-box, the accountable person decides. Endless debate blocks work, picking the cheapest tool ignores the rule, and letting everyone use a different tool breaks consistency.
7. A project manager takes over a project team after the previous project manager left. The team's last project failed, and team members say openly that they do not trust management. What is the best first step?
- A) Ask the sponsor to address the team
- B) Meet team members individually to listen to their concerns and build relationships
- C) Introduce strict reporting rules
- D) Replace the most critical team members
Show the answer and explanation
Correct answer: B
Listen individually and build relationships first.
8. Half of a project team works in the head office and half works remotely from three other cities. In a recent survey, the remote team members said they feel disconnected from decisions and from their colleagues. What should the project manager do?
- A) Require them to relocate
- B) Introduce regular video check-ins, virtual team-building and clear communication norms
- C) Reduce communication to save time
- D) Communicate only through formal reports
Show the answer and explanation
Correct answer: B
Regular video check-ins, virtual team-building and clear norms improve connection.
9. Two senior developers on a predictive software project disagree strongly about the system architecture. The argument has lasted a week and is now delaying the design phase. What should the project manager do first?
- A) Choose the architecture herself to save time
- B) Meet with both to understand their positions and facilitate a joint decision based on project objectives
- C) Escalate to the functional manager
- D) Tell them to compromise by splitting the difference
Show the answer and explanation
Correct answer: B
Resolve the conflict directly and collaboratively, using project objectives. Choosing herself alienates one side, escalation is premature, and splitting the difference can produce a weak technical solution.
10. A developer joins a hybrid project four months after it started. The project uses several tools and has detailed working agreements. What will most help the new developer become productive quickly?
- A) Assigning the hardest tasks immediately
- B) A structured onboarding with a buddy, access to project information and the team's working agreements
- C) Asking them to read every document alone
- D) Excluding them from meetings until they catch up
Show the answer and explanation
Correct answer: B
Structured onboarding with a buddy, access to information and the working agreements speeds integration. The hardest tasks at once are risky, reading everything alone is inefficient, and excluding them from meetings slows them down.
11. A hybrid team has members in two offices and several working from home. Some members expect instant replies to chat messages, while others check messages twice a day, and arguments have started. What is the best preventive tool?
- A) Ask the sponsor to set rules
- B) Ban instant messaging
- C) Let each member decide individually
- D) Agree communication norms in the team charter
Show the answer and explanation
Correct answer: D
Communication norms agreed in the team charter set expectations and prevent conflict.
12. An agile team includes members with all the skills needed to deliver a working increment. This is a:
- A) Functional team
- B) Matrix team
- C) Virtual team only
- D) Cross-functional team
Show the answer and explanation
Correct answer: D
A cross-functional team holds all skills needed to deliver an increment, reducing hand-offs.
13. A project team has been formed from staff of two companies that recently merged. In the first weeks, members are guarded and share little information with colleagues from the other company. Which action by the project manager most helps build trust?
- A) Monitoring everyone's work closely
- B) Keeping project information confidential from the team
- C) Rewarding only individual achievements
- D) Leading by example, keeping commitments and being transparent about decisions
Show the answer and explanation
Correct answer: D
Trust grows from leading by example, keeping commitments and being transparent. Close monitoring signals distrust, and withholding information or rewarding only individuals deepens the divide.
14. Who is responsible for ordering the product backlog in Scrum?
- A) The Scrum Master
- B) The development team
- C) The product owner
- D) The project sponsor
Show the answer and explanation
Correct answer: C
In Scrum the product owner is accountable for ordering the product backlog and maximising value.
15. A project's PERT analysis gives an expected duration of 30 days and a standard deviation of 4 days. The sponsor asks for the approximate probability of finishing within 34 days. What is it?
- A) About 84%
- B) About 68%
- C) About 50%
- D) About 95%
Show the answer and explanation
Correct answer: A
34 days is one standard deviation above the mean: 50% + 34% ≈ 84%. 68% is the ±1σ range and 95% is ±2σ.
16. A project must decide whether to build or buy a scheduling module. Building costs $120,000, with a 40% chance of $30,000 of rework. Buying costs $125,000, with a 10% chance of $50,000 of integration work. Using expected value, which option is preferred and at what expected cost?
- A) Build, $132,000
- B) Build, $120,000
- C) Buy, $130,000
- D) Buy, $125,000
Show the answer and explanation
Correct answer: C
Build: 120,000 + 0.40 × 30,000 = $132,000. Buy: 125,000 + 0.10 × 50,000 = $130,000, so buy is preferred. Figures without the risks are wrong.
17. A project must deliver a regulated hardware component with fixed specifications and a companion mobile app whose features are uncertain. Which delivery approach is most appropriate?
- A) A hybrid approach: predictive for the hardware and adaptive for the app
- B) Fully predictive for both
- C) Fully agile for both
- D) Kanban only for the hardware
Show the answer and explanation
Correct answer: A
Regulated hardware with fixed specs suits a predictive approach, while the uncertain app suits an adaptive one. A hybrid applies the right method to each part.
18. A city council is procuring a contractor to build a public library. Before bids are submitted, it invites all interested contractors to a single meeting where it explains the requirements and answers questions. What is the main purpose of this bidder conference?
- A) To ensure all prospective sellers receive the same information
- B) To negotiate the final price with one seller
- C) To award the contract
- D) To audit the seller's performance
Show the answer and explanation
Correct answer: A
A bidder conference ensures all prospective sellers receive the same information, keeping competition fair. Price negotiation, contract award and seller audits happen later.
19. Buying insurance against a project risk is an example of which risk response strategy?
- A) Transfer
- B) Avoid
- C) Mitigate
- D) Accept
Show the answer and explanation
Correct answer: A
Insurance shifts the financial impact to a third party, which is transfer. The risk itself remains, so it is not avoidance.
20. A regulator has imposed a completion date for a new water treatment plant. The project manager's schedule analysis shows a total float of −5 days on the critical path. What does this mean?
- A) The current plan misses an imposed date by 5 days
- B) There are 5 spare days
- C) The path is no longer critical
- D) Five activities can be removed
Show the answer and explanation
Correct answer: A
Negative float of −5 days means the plan misses the imposed date by 5 days, so compression or replanning is needed. The path remains critical.